From a BBS to a cutting plan
Prepare a bar bending schedule for optimization while preserving bar marks, quantities and approved developed lengths.
A bar bending schedule (BBS) describes the bars required by the drawing. A cutting plan allocates their developed lengths to the stock available in the yard. Keep the drawing revision and bar marks with the job throughout the conversion.
Prepare one fabrication group
- Select a single diameter, grade, coating and traceability group.
- Read the developed cutting length from the approved schedule. For a bent bar, the overall dimensions describe the finished shape. Its developed length includes the prescribed bend allowances.
- Check how the schedule defines quantity. Multiply bars per member by the number of identical members only if the schedule has not already totalled them.
- Import the rows or paste the lengths and total quantities. Check row counts and total linear metres before optimizing.
Check a two-mark schedule
Suppose marks B01 and B02 are both Φ16. B01 needs six pieces at 3,850 mm and B02 needs twelve at 1,950 mm. The batch contains 18 pieces and 46.50 m of finished bar. If the imported total is 5.80 m, the quantities were omitted.
After optimizing, add the pieces produced by all repeated patterns. They should recover the six B01s and twelve B02s. Send each bundle to bending with its original mark, shape, dimensions and revision.